A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

Use the graph of f(x) to evaluate the following:
This problem has been solved!See the answerIn sheep, coat color is influenced by two genes. Gene A influences pigment production, while gene B produces black or
"Oh, well," said the captain, soothing his children, "We'll get ashore all right." But there was that in his tone which made them think, so the oiler quoth: "Ye
Help with this question, ASAP PLEASE!!
when you use ____ you form general ideas and rules based on your experiences and observations a. symmetry b. logic c. deduction d. induction
For the instant represented, car has a speed of 100 km/h, which is increasing at the rate of 8 km/h each second. Simultaneously, car B also has a speed of 100 k
Can someone please explain to me how to solve this problem? Thank you.
Which expression is equivalent?
does the point (3,-1) lie on the circle (x+1)^2 + (y-1)^2=16
Complete the steps to factor 2x^2 + 6x + 5x + 15 by grouping. What is there greatest common factor of Group 1? A)2 B)x C)2x