if 25 worker need 3 days to build a house how long will 10 worker need

Respuesta :

sasukezwrldzxu
sasukezwrldzxu sasukezwrldzxu
  • 04-03-2021

Answer:

3 x 10 = 30 man-days per house

Answer Link
akbusiness987
akbusiness987 akbusiness987
  • 04-03-2021

Answer:

7.5 days

Step-by-step explanation:

Answer Link

Otras preguntas

the satellite moves at a speed of about 27,000 kilometers per hour. What are 4 numbers that could be the actual speed of the satellite
What is the narrator doing in the first paragraph of the end of the storytelling by Ernest Hemingway
A letter to europe from the united states costs $0.80 to mail. a letter mailed within the united states cost $0.37. nancy mails 5 letters for $2.71, some to eur
What are the coefficients of 60a+30c
What is a newly industrialized nation? a. a country with an agrarian based economy, but social and political progress. b. a country with a more advanced econo
What is negative 5/12 minus 7/9
This is slightly URGENT!! Help pleaseee :) Has any one read the great gatsby??? Which statement is incorrect concerning chapters 2 and 3? Select one: a. In both
When Mary was born she weighed 8lbs. when she was 10yrs. old she weighed 10 times as much. How much more did Mary weigh when she was 10 years old than when she
What epic offers insight into ancient greek culture, beliefs, and values?
How to write 792,065 in expanded form?