12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

Which of the kingdoms has the smallest number of known species
After what happened on April 19 can war between the colonies and Great Britain be avoided?
you measure or observe two events to occur at the same time one nearby and one further away. Which one did you actually see first?
After what happened on April 19 can war between the colonies and Great Britain be avoided?
If Walt can paint 25 feet of fence in an hour, and Joe can paint 35 feet in an hour, how many minutes will it take them to paint a 150-foot fence, if they work
If a slope of a line is 2/0 is it 0 or undefined?
Find all powers of 4 in range 4 through 1,000
Which of the following organisms can perform alcoholic fermentation? (1) yeast, (2) humans, (3) bacteria. a. 1 and 2 b. 1 and 3 c. 1 only d. 1, 2, and 3
you measure or observe two events to occur at the same time one nearby and one further away. Which one did you actually see first?
“The genetic code is universal.” Explain this statement.