8 students take 18 hours to construct a raft.
If the raft needs to be completed 12 hours earlier, calculate how many more students are needed.

Respuesta :

devishri1977
devishri1977 devishri1977
  • 04-08-2021

Answer:

16

Step-by-step explanation:

Students                      8       x

Time taken (hours)     18     18 - 12 = 6

If number of students increases, the work will completed in less hours.

So inverse proportion

[tex]x =\frac{18*8}{6}=3*8 = 24[/tex]

Additional students required = 24 - 8 = 16

Answer Link

Otras preguntas

plzzzzzzzzzzz help me!!!
Is it worth spending millions of dollars to explore space today? How could you connect European exploration to space exploration today? Explain in at least 1 FU
The male red-winged blackbird has a bright-red patch on its shoulder. This adaptation increases its chances of mating with the female blackbird. Some of the bir
A high school student refuses to participate in the Pledge of Allegiance at the beginning of the school day. A teacher screams at the student and says that the
find the difference -10-(-7)=
Plz help, first brainliest
Which of the following business that is owned and operated by a single person
What is the main idea of "The Fall of the French"
Though none of the religion teaches wrong, why do people involve in immoral work? Answer logically.​
do u guys know why.............................