In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

How is augmented reality used A) to integrate 3-D graphics for providing a live, direct, or indirect view of a physical real-world environment B) to gather and
How does loosening a string on a guitar affect its natural frequency? 1) decreases 2) increases 3) stays the same 4) fluctuates
Explain how to determine the wavelength of a wave.
What did the prince do whenever he found a girl who might be cinderella
Which area of earth is most similar to the suns convention zone
An earthquake is best described as a Short term Long term Global Climatic
A worldwide resource concerned with the care of children is A) WHO B) CDC C) UNICEF D) FDA
graph[tex]y = |x| - 1[/tex]
What started the Great Depression? What day did this happen? What was the nickname for this day?
Why might alexandria choose a local movie theater when she could see the same movies for less at a corporate establishment? getting the lowest price on theater